Design-build addition to residence, Ithaca, NY
[Addition homepage]
Week 10: August 9 - August 15, 2004
[previous week] |
[next week] |
[week by week index]
We have almost completed the sheathing on the exterior walls. Shown here is the new level of scaffolding which makes it possible to install the top layer of plywood; and some more Tyvek.
We built lots of scaffolding this week; shown at left (looking up) are some temporary sliding platforms within the 3-foot zone between the existing house and the main part of the addition.
We also constructed the mezzanine within the big studio space, shown in the foreground covered by a blue tarp. During construction, we use these various platforms to bring plywood sheathing up to the scaffolding.
[previous week] | [next week] | [week by week index]
last updated: 16 August 2004